New Dining and Teaching Block 


 
 

Please see architect images below of what the new building is planned to look like. It will include dining and kitchen facilities, a mix of new teaching spaces, small group rooms and external teaching terraces on the first and second floors. New link bridges will also be in place connecting both schools to the new building.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

January / February 2022 (Week Beginning 31st and 7th)

Areas being excavated ready for the building foundations to be laid

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The concrete is being delivered. Work on the foundations is progressing well

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 14th Feb)

The foundations are close to completion, we expect the steel work will soon commence

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 21st and 28th Feb)

The steel work has now commenced, progressing very well

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 7th March)

The steel work is still underway, stairs are now being implemented onto the build

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 14th and 21st March)

Piping work is now being added to the build

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 28th March)

Piping work continues, floor work has now also commenced

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 04th April)

Concrete will soon be added to each floor of the build

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 11th and 18th April)

The concrete floors are now complete, brickwork has now commenced

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

(Week Beginning 3rd May)

Brickwork continues, secondary steels are being put in place ready for insulation